Project Name: Bathurst Bridge (New), BATHURST
Date of Project: July 2007 (3 weeks to complete)
Project Description: Major Grouting between Bridge Planks – DMR
- Testing procedure on site to ensure the MDP process of grouting is successful
- Follow this successful procedure as the bridge is being constructed using non shrink epoxy grout
- Grouting between large concrete bridge planks following the fitting into position by way of very large crane
- MDP technicians carrying out the work were highly commended by DMR Engineers due to their precision and skills during the project and importantly within the programme time.
Project Value: $300K