Project Name: 26 Ozone St, Cronulla (Stage 1 & 2)
Date of Project: June 2010 – March 2012
Project Description: Main Building Works, Fire Services Upgrade & Balcony Reconstruction
- Concrete Spalling repairs
- Plaster and painting works
- Re-pointing & reconstruction of Brickwork
- Crack stitching & crack repairs
- Cavity flashing replacement
- Lintel replacement
- Installation of new cavity wall ties
- Replacement of windows and balcony sliding doors
- Rendering of external façades
- Application of weather resistance façade coating
- External painting
- Installation of fire hydrant & drencher system
- Balustrade replacement, demolition & reconstruction of balconies
- Roof slab edge works
- Replacement of furring channels including: flashing, gyprock, painting, skirting boards etc.
Project Value: $2.3 million (both stages 1 & 2)